WIND -- October 21st turbine installation began.
Placement of UUAA’s small wind turbine is on the highest ground with clearest surroundings that comply with Township requirements (pictured on 10/21/10 are Dave Friedrichs, as general contractor, and Matt Tripp from electrical wholesaler McNaughton-McKay) |
|
Toledo Caisson’s rigs can auger footings up to 14 feet in diameter, with this one for UUAA being just 42” wide. | |
. . . and 12 feet deep, with a steel cage insert and engineered anchor bolts patterned to accommodate the monopole being manufactured to hold the UUAA turbine. | |
The hole. | |
A level foundation ensures a plumb monopole (when set after a curing time frame of several weeks). | |
SOLAR-- November 5th installation.
Photo voltaic (solar) panels were installed on the south side of the building on November 5th. In this photo the installation team celebrates the accomplishment! |
|
First clamps were installed on the roof. | |
Crossrails secure the 48 solar panels, representing 10,800 watts of energy. | |
On November 8th Don Winsor installed data cards in grid-tie invertors to monitor solar energy output. | |
NOV 12 - The Monopole Arrives |
|
The 80' monopole was unloaded on the Ellsworth side of the parking lot. In the foreground is the base for the monopole. | |
Our minister then, Rev Gail Geisenhainer checks out 6’ rotors (blades) of Xzeres #110 turbine (2.5 kw) with Eric Ericksen and Mark Doman | |
10.8 kilowatts of roof top solar panels are now visible from the labyrinth behind the Social Hall | |
Closer view of the solar panels where Tim Neff and Hal, members of Homeland Builders Group were installing the PV wiring |
|
11/19 - 2.5 Kilowatts Set and Sound | |
11/19 - Engineering Expertise | |
11/19 - Got Crane - Will Travel | |
11/19 - John Wakeman of SUR Energy summiting Mount UU | |
11/19 - The Renewable Energy Project Foursome | |
11/19 - Climbing Mount UU |